a contactor hired 150 men to pave a road in 30 days.how many mem will be hire to do the same work in 20 days​

Respuesta :

kevinmario2008 kevinmario2008
  • 05-12-2021

Answer:375

Step-by-step explanation:W = RTN

1 = 1/7500(20)N

1 = 20/7500N

1 = 2/750N

750(1 = 2/750N)

750 = 2N

750/2 = N

375 = N

There are 375 men to do the job in 20 days

Answer Link

Otras preguntas

what is the value of the expression 5x − y when x = 3 and y = 1? 14 10 7 0
Name three hotter 50-year-old celebrity babes, please?
list the fractions and decimals in order from least to greatest ...0.6, 5/8, 7/12, 0.72
mi primo y yo conocemos a los jugadores del real madrid. ellos __________.
Light traveling though air strikes the surface of the four different materials shown. Which material reflects light but does not refract it?
what is a mastaba?- stepped pyramid- simple tomb- valley temple
over the past ten years, the town's population doubled in size. the population is currently 12,000. what was the population ten years ago?
2v + 3 > 4 1/3 solve for v
22. how are quantitative and qualitative data different? (chp 1 notes)
what is the meaning of the underline word suppliant of act i, scene i, of richard iii?