15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Respuesta :

ridmitharuka
ridmitharuka ridmitharuka
  • 02-08-2021

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

Answer Link

Otras preguntas

Evaluating audience feedback to your speech presentation usually happens: A. before the speech. B. after the speech. C. during the speech. D. in the speech prep
Study figure 17 above over time what will happen to the river bank at B why
What are the solutions of the inequality? Graph the solutions. x/5 > -2
you have 120 pieces of fabric to make a blanket. each piece of fabric is a square with a side length of 6 inches. you use as many pieces of fabric as possible t
Which statement about direct objects is true
Write the point-slope form of the equation of the line passing through the points (-5, 6) and (0, 1).
Why do people bully for power?
what are four temperate climate
A small business employs 7 women and 3 men. The manager randomly selects 3 of them to be on a team. What is the probability that all 3 are women?
Someone who wants to make a safe (not risky) investment might consider putting his or her money into _____ or _____. stocks, the bank stocks, bonds bonds, the b