thirty-six men can paint a shopping mall in 25 days. How many days will it take 15 men to paint the mall, if they work at a same rate?​

Respuesta :

ksperu ksperu
  • 04-05-2021

Answer:

12.5 days

Step-by-step explanation:

Given

No of workers= 30

Time taken to paint shopping mall= 25 days

Assume time taken for 15 men =X

Time taken for 15men to paint X= (15*25)/30

=12.5 days

Answer Link

Otras preguntas

help!!!!!! what is 3/4 + 1/12?
A student studying primary succession should focus on which of these communities?​
In a Gram staining procedure, what is the color of a Gram negative bacterium observed under a light microscope?
An idea,theme,or image that begins and ends a text can be referred to as a
why dont lou and the narrator carry out their plan to recapture the wall
4 less than a number n is -15 N= ?
That district court was hated and distrusted by
Which of these vocabulary words would be an appropriate description of a clown? droll bohemian imperceptible rancorous
Why did the workers in the steel plants go on strike in 1919?
How many solutions does the equation 4x + 8 = -2 - 2 + 5x have? (5 points) Two One None Infinitely many